Recovering a Delay Mid-Commissioning: A Corporate Fit-Out in Hyderabad

Helping a 110,000 sq ft corporate fit-out reach handover on schedule through structured commissioning and integrated systems testing.

Recovering a Delay Mid-Commissioning: A Corporate Fit-Out in Hyderabad
Project Type

Corporate Fit-Out

Location

Hyderabad, India

Area

110,000 sq ft

Sector

Banking and Insurance

Engagement

Commissioning and Testing

Project Stage

Testing, Commissioning and Handover

The Client's Objective

For a banking and insurance client, the priority was clear: bring a 110,000 sq ft corporate workplace through testing and handover within the required contractual timeline. With multiple building systems needing to perform together before occupancy, the project required close coordination, structured testing, and clear visibility of what remained to be resolved.

Beratung's Approach

Beratung was brought in to provide dedicated commissioning oversight and bring structure to the testing and handover process. The team worked closely with the project stakeholders to validate design intent, establish daily commissioning targets, and track open items through to closure. This created a clear line of sight from testing activities to the final handover requirements.

Putting the Systems to the Test

The commissioning process also created opportunities to test systems beyond the immediate handover requirements. Ahead of critical-room handover, Beratung recommended UPS load testing to verify system performance under load. The testing identified issues that could have affected equipment reliability if left unaddressed.

During integrated systems testing, the team also verified the interaction between the fire alarm and shutdown systems, identifying a delay in the shutdown response and resolving it before closeout.

The Outcome

The project reached handover within the required timeline, with an initial 10-day delay fully recovered during the commissioning phase. The engagement demonstrated the value of structured commissioning in bringing multiple building systems together, resolving issues before closeout and giving the client greater confidence in the facility's readiness for occupancy.

The client's feedback highlighted Beratung's technical understanding of MEP systems and collaborative approach to problem-solving as key strengths of the engagement.