Hyperscale Data Center Commissioning Under Pressure
Bringing commissioning discipline and issue resolution back in line with a critical project schedule.
Bringing commissioning discipline and issue resolution back in line with a critical project schedule.

Hyperscale Data Center
Hyderabad, India
9.6 MW
Commissioning and Site Coordination
Construction and Commissioning
The 9.6 MW hyperscale data center was already under construction when the project schedule began to slip. With commissioning milestones approaching, unresolved issues were putting further pressure on the timeline. The project was being delivered through an EPC partner, with another consultant already on site. Beratung's role was to bring greater discipline to the commissioning process and ensure issues were identified and resolved before they affected subsequent stages.
Beratung took ownership of the commissioning process and site coordination. The team established daily target meetings, tracked risks and open issues through to closure, and maintained close coordination across the teams involved. The approach focused on identifying problems early and resolving them before they could compound during later commissioning activities.
During the facility's 9.6 MW load test, several sensor malfunctions threatened to disrupt the milestone. The team traced the faults, coordinated the required replacements, and completed the retest without losing the milestone. The early-detection approach also reduced recurring commissioning issues by approximately 30% over the course of the project.
A delay initially projected at around 32 days was brought down to approximately 15 days. The engagement subsequently led to further Beratung work for the client in another region, reflecting the value placed on the team's technical depth and execution discipline under schedule pressure.