Factory-Calibrating VAV Boxes to Streamline Air Balancing

Moving part of the air-balancing process upstream to reduce commissioning time on a fast-track project.

Factory-Calibrating VAV Boxes to Streamline Air Balancing

The Commissioning Requirement

Air balancing had been identified early as a potential bottleneck on a fast-track project. With multiple pressure-independent VAV boxes requiring balancing, the conventional approach could add significant time to the commissioning programme. The team looked for a way to complete more of the preparation before the equipment reached site.

Preparing the VAV Boxes Off Site

The VAV boxes were calibrated at the factory for their target site airflows before dispatch. Each box was also labelled against the HVAC layout, with its intended minimum and maximum airflow clearly identified. This created a simple verification point during installation and made it easier to identify if a box had been installed in the wrong location.

Automating Branch-Level Balancing

Once on site, the pre-calibrated boxes were powered up and brought online through the VAV integrator. With the required minimum temperature setpoint applied, the boxes could self-balance at the branch level. This reduced the amount of manual balancing required on site, leaving diffuser-level balancing as the remaining manual activity.

The Impact

The approach reduced the time required for air balancing and also helped establish AHU fan speed and static pressure setpoints as part of the same process. By moving calibration upstream and using automated branch-level balancing on site, the team reduced the amount of commissioning work that needed to be completed manually during the project schedule.