Catching a Chilled Water Shortfall Before Construction

Identifying a chilled water flow mismatch during design review before it reached site.

Catching a Chilled Water Shortfall Before Construction

The Design Requirement

During a design review for a multi-building campus, Beratung identified a mismatch between the chilled water flow the pumps were designed to deliver and the total flow required by the campus cooling loads. Although the difference appeared relatively small at the design stage, the available pump flow would not have matched the total system demand.

Reviewing the System as a Whole

The review compared the total pump flow against the combined chilled water requirements across the campus. This identified the shortfall before equipment procurement and installation, when changes to the design could still be made without affecting site execution.

The Design Adjustment

The pump flow rates were revised in the next drawing revision so that the total chilled water supply matched the overall demand across the campus.

The Impact

The mismatch was resolved before any pumps were ordered or installed, avoiding the need to address the issue after construction. The case demonstrates the value of detailed design review in identifying system-level inconsistencies early, when they can still be corrected through the design process.